Contact UsMIT MITei

Quest Fact Sheet: Carbon Dioxide Capture and Storage Project

Fact Sheet: Carbon Dioxide Capture and Storage Project

Company/Alliance: Athabasca Oil Sands Project: Shell Canada, Chevron Canada and Marathon Oil Sands

Location: Shell’s Scotford Upgrader, located near Fort Saskatchewan, Alberta, Canada

Start Date: Start injection (2015)
Quest was approved by Alberta Government in 2012, and Shell has made the final decision to go ahead with the project

Size: 1.1 Mt/yr (35% capture)

CO2 Source: The Scotford steam methane reformer units, which produces hydrogen for upgrading bitumen (capture using amine technology)

Storage: 65 km onshore pipeline to onshore saline aquifer at a depth of 2km (Cambrian Basal Sands) and possible EOR

 

Motivation/Economics:

Total cost of the project is estimated at $1.35 billion. Canada and Alberta governments are to invest C$865 Million (October 2009). The project was also awarded C$120 million from the Clean Energy Fund (a fund established by the Canadian Government to demonstrate CCS technology). The Alberta Government has offered to provide $745 million to the project.

Shell filed its regulatory application for Quest on November 30, 2010, after the Alberta Government released The Carbon Capture and Storage Statutes Amendment Act, 2010 which guides how large scale CCS projects will proceed in Alberta. The DNV issued its first certificate of fitness for CO2 storage for Shell's Quest project in November 2011.

In September 2012 the Quest project received approval from Alberta's Energy Resources Conservation Board. Shell says it now has all the necessary federal and provincial regulatory approvals in place and construction, which will take roughly 30 months, has already started.

Comments:

This is part of the Athabasca Oil Sands Project. Currently there are 3 test wells being drilled at the injection site 90 km north. CO2 transportation is planned to be via pipeline to the injection site. The target reservoir is the Cambrian Basal Sands at a depth of 2,000 – 2,500 metres (6500-8000 feet).

Depending on the data obtained from these test wells and other development work, Shell plans to apply to Alberta Environment and the Energy Resources Conservation Board for regulatory approvals in 2009. Pending regulatory approval, Shell and its joint venture partners would make a decision on whether to proceed with the project. If approved, the project could become operational within three to five years.

Shell began its production from Scotford oil sands upgrader expansion project on May 2011. This increases Scotford's bitumen upgrading capacity to 255,000 b/day.

In April 2012, a screening report released by Natural Resources Canada and the Canadian Transportation Agency concluded that the proposed Shell Quest CCS Project is not likely to result in significant adverse environmental effects, with the implementation of the appropriate mitigation measures.

In August 27, 2014, Shell Canada fitted the final module at the Quest CCS project, putting start-up on track for 2015.

The Quest CCS project, now 70 percent complete, is being built with funding from the Alberta and Canadian federal government to help mitigate greenhouse gas emissions from the oil sands.

Project Link: Shell Quest CCS website

Other Sources and Press Releases:
Shell fits final module on Alberta oil sands' first carbon capture project (August 2014)
KBR Canada wins module-building contract for Shell’s Quest carbon capture and storage project (April 2013)
Fluor to Build Shell's Quest Carbon Capture Facility in Canada (October 2012)
Shell starts quest for first carbon capture oil sands project (September 2012)
Carbon capture project inches closer to construction (April 2012)
DNV Issues First Certificate of Fitness for CO2 Storage (November 2011)
Shell begins production from Scotford oil sands upgrader (May 2011)
Shell's Quest project starts (September 2010)
Canada and Alberta to invest C$865M (October 2009)
Government moves forward on carbon capture projects (June 2009)

Date Modified December 3, 2014